Arbre Project, Eggborough
Scope
Complete Installation of a willow burning gasification power plant including 6.6, 11 & 3.3Kv transformers, switchgear, MCC’s, DCS system, cable systems and instrumentation.
Connah’s Quay Power Station
(Combined Cycle Power Plant) E-ON (UK) Ltd
Scope
Individual replacement of the existing EGT Microlec steam turbine control system with an ABB Harmony Distribution Control System on each of the four 350MW units. Individual transfers were executed and commissioned during four planned station outages.
Kirklees (SITA), Huddersfield Waste to Energy Plant
Scope
Complete installation of the following ABB equipment: 11kV switchgear, 415v MCC’s, Transformers, Power Distribution, DCS systems, site wide cabling, containment and instrumentation.
Little Barford Power Station
Scope
DC Battery back-up system installation incorporating a blackstart facility
Drax Power Station
Scope
Flue Gas Desulphurisation DCS system cabling and instrumentation, plus materials handling installation