Oil and Gas Project

Holford Gas Storage Facility

Scope

Telecommunications installation including: Perimeter intrusion Detection system, CCTV system, Building intrusion detector system and a Radio and Antenna system.

Total E&P UK, St Fergus Gas Terminal

Scope

Replacement of Mod300 control system to AC460 controllers with S800 I/O modules. 34 new cabinets, 5650m of fibre optic cable, Cat 5 cable and 157 I/O cordsets were installed. 33 old cabinets were removed and redundant equipment in 46 control panels was stripped out.

Baku-Tbilisi-Ceyhan Pipeline Installation

Scope

Supply of Supervision and Instrument Commissioning Technicians for the Installation of the DCS Instrumentation along the 1300 mile stretch of new Oil Pipeline from Azerbaijan to Turkey.

De-Ruyter Oil Platform

Scope

Responsible for the complete field cabling design and containment for the DCS, ESD, F&G and the Foundation Fieldbus cabling

British Gas (HRL) Morecambe Bay

Scope

Replacement of Ferranti System for a new ABB DCS System both onshore and offshore. Total I/O count of 14,000. The Project consisted of 5 remote drilling platforms, 1 Central Control Platform and 1 Accommodation Platform

Comments are closed.